USPFO Energy Upgrades

Energy Upgrades to Multiple Buildings. Work includes Design service and Consisted of HVAC systems, Plumbing, & Electrical; Retrofit Lighting, Replaced Boilers with New Energy Efficient Boilers, Replace Water Heaters, Replaced HVAC units, Replaced Existing Pump Motors with New Variable Frequency Drive, Pump Motors. Project was completed on time within the Contract performance period.

Location: Gowen Field, Boise, ID
Customer: Idaho Air National Guard
Contract Amount: $1,198,803

Runway Maintenance

Various Maintenance Functions that keep RGAAF operational.

Re-marked all line markings

Repaired various concrete patches on runway tarmac.

Demoed and repaired 64,000 lf of concrete control joints.

Cleared 18 miles of weeds.

Location: RGAAF, Fort Hood, TX
Completion Date: November 2013
Customer: Army MICC Fort Hood
Contract Amount Final: $1,827,077

KI17010 Samuel Adams Brew Pub – NAF Ft Hood

NNAC performed this project as a design-build to renovate one of the oldest buildings on Fort Hood into a Sam Adams Brewery pubs. NNAC addressed several building deficiencies during construction including asbestos and mold abatement, structural repairs, and correcting pre-existing electrical issues that had been out of code for decades. NNAC worked closely with several involved parties to include the pub management, facility owners, DPW, Sam Adams Brewery and their contracted interior decorators to deliver an end product that met everyone’s needs and showcased the pub’s unique character and themes.

MWR Track and Field

MWR Synthetic Multipurpose field and running track. Design/Build project to remove two existing softball fields and construct a new multipurpose artificial turf sports field, a 6-lane, 400-meter synthetic running track, as well as activity lighting & scoreboard.

Prior to the new construction, the site was experiencing significant drainage problems and the fields would flood after rainfall. Design addressed this issue with installation of a new under-field drainage system.

The project also provided new field wash-water system, outer perimeter irrigation, underground electrical distribution system, activity lighting & scoreboard, 10’ high chain-link fencing, asphalt paving & concrete curbing, and landscape restoration.

“We greatly appreciate the quality, efficiency, and level of effort NNAC consistently provides and look forward to collaborating on future projects.”

Dawn Malveaux, Contract Specialist NAVFAC Northwest PWD Everett Naval Station

Location: Everett Naval Base, WA
Completion Date: August 2013
Customer: NAVFAC Northwest, PWD Everett
Contract Amount Final: $1,991,406

Repair Company HQ Building

The work included Demolition, Concrete, Framing, Roofing, Masonry, Doors and Windows, Insulation, GWB, ACT, Flooring, Painting, Mechanical, Networking, Electrical, Plumbing, Fire Suppression.

“The variety of construction services provided by Mrs. Lettau’s company has been exemplary, consistently on time, and within budget, always going beyond our expectations. I commend their dedication and commitment to providing quality construction services to the US Army at Fort Hood.”

–Mario Gonzalez, Contracting Officer

Location: Fort Hood, TX
Completion Date: May 2013
Customer: Army MICC Fort Hood
Contract Amount Final: $2,715,000

MW Dog Kennels Building 5005

Provide Temporary Facility/Shelter/Service during construction, demo, new construction of kennel facility, structural, roofing, masonry, doors, windows, finishes, fencing & MEP’s.

Location: Fort Hood, TX
Completion Date: May 2013
Customer: Army MICC Fort Hood
Contract Amount Final: $715,000

KS18001 Repair Drainage B & D NFH

This project is currently ongoing and is part of a Department of the Army funded program to improve drainage failures for the entirety of the North Fort Hood campus that covers over 4 square miles. The training area is extremely flat, so the drainage improvements are being successfully constructed within extremely tight tolerances. In addition to taking on over $1.5M in extra work due to various unforeseen utility conflicts, NNAC has worked closely with Fort Hood DPW to come up with unique and creative solutions to address improved drainage at locations where available space is extremely limited and shallow, while also reducing surface erosion issues.

Repair Building 37010

HVAC

Electrical

Insulation

Paint

Renovate Interior Walls

Location: Fort Hood Bldg. 37010, Fort Hood, TX
Completion Date: May 2012
Customer: Army MICC Fort Hood
Contract Amount Final: $1,038,878

KI17003 Rehab Landfill Lake Dam

This project was directed awarded to NNAC as an emergency repair project. The dam had failed after continuous heavy rains, causing the dam and spillway to breach with floodwaters and cause damage to downstream facilities. NNAC worked diligently with DPW and subcontractors to expedite the repairs, working extended hours and weekends, completing the construction scope and preparing the lake for resumed water retention in less than 4 weeks.