NNAC_Construction_Coeur_d_Alene_Boise_Idaho_Texas_Construction_Management_Design_Build_Heavy_Civil_Work_MWR_Track_and_Field_Everett_Naval_Base_Washington_1

MWR Track and Field

MWR Synthetic Multipurpose field and running track. Design/Build project to remove two existing softball fields and construct a new multipurpose artificial turf sports field, a 6-lane, 400-meter synthetic running track, as well as activity lighting & scoreboard.

Prior to the new construction, the site was experiencing significant drainage problems and the fields would flood after rainfall. Design addressed this issue with installation of a new under-field drainage system.

The project also provided new field wash-water system, outer perimeter irrigation, underground electrical distribution system, activity lighting & scoreboard, 10’ high chain-link fencing, asphalt paving & concrete curbing, and landscape restoration.

“We greatly appreciate the quality, efficiency, and level of effort NNAC consistently provides and look forward to collaborating on future projects.”

Dawn Malveaux, Contract Specialist NAVFAC Northwest PWD Everett Naval Station

Location: Everett Naval Base, WA
Completion Date: August 2013
Customer: NAVFAC Northwest, PWD Everett
Contract Amount Final: $1,991,406